How to apply microcement.

Four steps, four to seven days between the primer and first use. Read the full method below or ask our team for the technical data sheets.

  1. 01

    Prepare the substrate

    Clean and degrease tiles, plaster or concrete. Repair any cracks. Lightly sand glossy surfaces. Apply KCBerry Primer (KC Primer, the KCBerry Adhesion Promoter) and leave to dry for 4 hours. On wood, only prepared MDF is suitable — always primed with KCBerry Primer; other wood is excluded.

  2. 02

    Apply Microbase (3 coats)

    Apply the first coat of Microbase with a trowel, embedding the fibreglass mesh. Leave to dry for 12 hours, then sand with 80 grit. Apply the second and third coats of Microbase, sanding with 80 grit after each. Mix 3.0 L of Royal Resin per 10 kg of Microbase powder. For MicroNoSlip, omit Microbase and fibreglass mesh entirely; always apply KCBerry Adhesion Promoter (primer) first, then three coats of MicroNoSlip directly, using 2.7 L of Royal Resin per 10 kg of powder.

  3. 03

    Apply Microfinishing or Microtraffic (2 coats)

    Apply the chosen finish in a thin layer with a stainless-steel trowel. Allow 6 to 12 hours of recoat time between coats. Sand lightly between each coat; use grit 120 for Microfinishing. Microfinishing consumes 1.0 kg/m² for the two coats: a 15 kg bucket covers 15 m². Per 10 kg of powder, use 4.5 L of Royal Resin for Microfinishing or 3.7 L for Microtraffic. For the direct three-coat MicroNoSlip system (anti-slip class R11), skip this separate finishing stage.

  4. 04

    Varnish

    Apply the first coat of two-component polyurethane protective varnish. Wait 4 hours. Apply the second coat of varnish. Leave to dry for 24 hours before light use, and 7 days before heavy traffic or contact with water.